City of Medicine Hat’s Southwest Substation to begin construction in June

21d 6h ago by lemmy.ca/u/devrandom in medicinehat@lemmy.ca from chatnewstoday.ca

Construction on Medicine Hat’s Southwest Substation project will begin in June 2026.

The City of Medicine Hat received approval from the Alberta Utilities Commission for the construction and operation of the facility on April 25, 2025.

The substation, known as MHS-11, is located west of Gershaw Drive and Highway 3, just north of Saamis Prairie View Cemetery.

In early June, the City says you will see increased on-site activity, with crews bringing in machinery and starting the groundwork to prepare for construction.

The City says the project is part of its long-term planning to support growth and maintain reliable electric service for customers across the community.